Undertaking a renovation of your Kitchen Toronto is not an easy task. You need to find a Kitchen company that will stick to the deadline and does high-quality work at an affordable price. To be able to finish and help you achieve your dream kitchen in time takes about a month. Before you undertake your kitchen renovation, you must understand what happens during the procedure.
Step1: Hiring and ordering
The very first step to kitchen renovation is hiring a kitchen contractor and designing your new kitchen. Once that has been done, all the necessary materials would be ordered. It can take up to a month, depending upon where you are ordering from.
Step2: Tearing down the kitchen
It takes about three days to tear down the old kitchen or make the structural changes needed, like moving the location of the window or a wall. During this stage, all existing countertops, cabinets, appliances, and flooring are removed. This step is carried out only by the professionals.
Step3: Changing Locations
During the renovation, if you are planning to change the location of the plumbing and other utilities, that can take about 2 to 5 days. The electrician takes about a day or two to relocate the electrical outlets and power feeds.
Step4: Repainting
Repainting the kitchen can change the way it looks. It takes about two to three days to finish painting.
Step5: Prepping of the dry walls
Once the walls have been painted, the dry walls need to be prepped, installed, and primed, and this could take a couple of days.
Step6: Installation of the floor
Installing the kitchen floor can take up to a day or two, depending on the chosen material and the area that needs to be covered.
Step7: Cabinets
Installing cabinets can take up to 4 days. The installation time is dependent on whether you have opted for custom-made cabinets or have chosen prefabricated ones. If the cabinets’ installation is complex, it will impact the time taken to install them.
Step8: Countertops
Countertop installation takes about a day or two. However, during the period when the countertop is being fabricated, other tasks would continue.
Step9: Plumbing and electricals
It takes about a day or two for the plumbing installations. Once that has been done, HVAC and other electrical systems are installed, which would take about two days. It takes approximately a day or two for all the electrical appliances to be installed. This can only be done once all the utility connections have been established.
Step10: Backsplash
If you want to get a backsplash, it can take about a day or two, depending on the material and design which is being installed.
Step11: Finishing touches
In the final step, the sink and other appliances which aren’t affected by the installation of the countertops are installed. This takes around two days. Finishing carpentry is done in which the floor trim, cabinet adjustments, molding details, and other details. It takes approximately four days to do the final touches.